Caltrans District 4 (bot) · @CaltransD4_bot
105 followers · 59 posts · Server m.ai6yr.org

: The rebar crew is working hard and are right on schedule. The rebar will help keep the pavement from caving in. ⁦@CaltransHQ⁩ ⁦@KCBSRadio⁩ ⁦@511SFBay⁩

#680paving

Last updated 2 years ago

Additional images for work on I-680 Northbound in Alameda County on Sunday. Paving work is going well, and Caltrans remains on schedule during the holiday weekend. ⁦@CaltransHQ⁩

#680paving

Last updated 2 years ago

Caltrans crews are busy again pouring concrete for the project on I-680 in Pleasanton and Sunol in Alameda County. Warm weather all day allowed Caltrans to stay on schedule over the holiday weekend.

#680paving

Last updated 2 years ago

Caltrans has placed about 4,000 of the 7,500 feet of concrete so far on I-680 in Alameda County. Caltrans is scheduled to pour again around 1 p.m. on Sunday (today). There have been no safety issues or collisions in the construction zone, and work is on schedule.

#680paving

Last updated 2 years ago

: Sun Feb 19 UPDATE; NB I-680 btwn Pleasanton & Sunol remains closed til Tu. Feb 21 at 5AM. Caltrans placed 4,000-7,500 ft of concrete so far. Detours in place. Check Caltrans Quick Map for latest road conditions.

#680paving

Last updated 2 years ago

A few more videos from : Caltrans crews working hard on Saturday afternoon. Closure on NB I-680 between Pleasanton and Sunol until Tuesday, Feb. 21 at 5 a.m. Use alternate routes. @CaltransHQ

#680paving

Last updated 2 years ago

: NB I-680 crews laying down asphalt. Closure on NB I-680 btwn Pleasanton & Sunol til Tues Feb 21 at 5AM. Caltrans repaving work. Use alternate routes. @CaltransHQ @CHP_ContraCosta

#680paving

Last updated 2 years ago

: NB I-680 UPDATE Sat Feb 18. Crews paving closed section of NB I-680 in Pleasanton-Sunol Work. NB I-680 is scheduled to re-open early Tuesday morning. @pleasantonpd @CHP_ContraCosta

#680paving

Last updated 2 years ago

: Crews began pouring liquid concrete Saturday night into early Sunday morning. NB I-680 is scheduled to re-open early Monday morning.

#680paving #concretepour #construction #california #alamedacounty

Last updated 2 years ago

: The rebar installation has been completed and ready for the liquid concrete pour this evening. Installing the rebar will give the new roadway more strength, more lifetime expectancy, and a smoother ride for motorists who travel along NB I-680

#680paving #alamedacounty

Last updated 2 years ago

: NB I-680 from State Route 84 to Sunol Blvd is completely CLOSED until 5 A.M., Mon. Feb. 13. Motorists are encouraged to plan ahead and use the recommended detour route. The traveling public can also access NB I-238 to I-580, I-580 & I-880.

#680paving #detour #sunol #alamedaco

Last updated 2 years ago

: The rebar installation has been completed and ready for the liquid concrete pour this evening. Installing the rebar will give the new roadway more strength, more lifetime expectancy, and a smoother ride for motorists who travel along NB I-580.

#680paving #alamedacounty

Last updated 2 years ago

: Crews are laying down the hot mix, which will help cool down quicker. This will allow crews to install rebar. NB I-680 will remain closed until 5 A.M., Mon. 2/13. SB I-680 is open. For the latest traffic conditions ▶️quickmap.dot.ca.gov

#680paving